Read the question as text

Q58. The horizontal and vertical axes of an Operating Characteristic (OC) curve in quality management generally represent the percent defective of a lot and the success rate of a lot, respectively. Samples of size n are extracted from a lot of size N. When the number of defective samples is less than or equal to the pass quantity C, the lot is considered to have passed; otherwise, it is considered to have failed. Which of the following is a diagram that shows the trend of change in the OC curve when N and n are fixed and C takes the values 0, 1, and 2?

The original image above preserves the complete exam wording and layout.

Choose your answer
Choose an option to check your answer.
1 / 2

Source: 2025A_FE-A_Questions.pdf, PDF page 25. ID: 2025A-A-Q058. Explanation written for this textbook.

Original question · Q58
Q58. The horizontal and vertical axes of an Operating Characteristic (OC) curve in quality management generally represent the percent defective of a lot and the success rate of a lot, respectively. Samples of size n are extracted from a lot of size N. When the number of defective samples is less than or equal to the pass quantity C, the lot is considered to have passed; otherwise, it is considered to have failed. Which of the following is a diagram that shows the trend of change in the OC curve when N and n are fixed and C takes the values 0, 1, and 2?

Scroll horizontally to read the image at full size.