Which of the following is the appropriate combination of the earliest and latest node times on the node N4 in the arrow diagram shown in the figure? Here, node N1 starts at time 0. Earliest node time Latest node time

The original image above preserves the complete textbook wording and layout.

Choose your answer
Choose an option to check your answer.
1 / 1Back to lesson →

Source: FE Vol 2.pdf, PDF page 138, textbook p. 134 · Information-technology Promotion Agency, Japan · First Edition: April, 2015. ID: tb-v2-c1-q14. Publisher answer and commentary · private review.

Original question · Q14
Q14 
Which of the following is the appropriate combination of the earliest and latest node times on 
the node N4 in the arrow diagram shown in the figure? Here, node N1 starts at time 0. 
 
 
 
 
Earliest node time 
Latest node time 
a) 
5 
 8 
b) 
5 
10 
c) 
8 
 8 
d) 
8 
10