CONCEPT PRACTICE

Earliest node time

2 related verified questions. Take them one at a time.

Filter questions
Question sources

2 of 2 questions match.

ITPEC Practice
0/1 answered
Textbook Exercises
0/1 answered

Question 1 of 2

0/2 answered

2024 Spring · Subject A · Q41

Original exam question · Select the image to enlarge
Read the question as text

Q41. The activities and milestones of a project are shown in the arrow diagram below. Which of the following is an appropriate description of the project if the duration of activity B is increased by 5 days? B F A 5 20 10 E H 10 15 C G 10 D 15 25 Legends Activity name Number of days required Dummy activity

The original image above preserves the complete exam wording and layout.

Choose your answer
Choose an option to check your answer.
1 / 2

Source: 2024S_FE-A_Questions.pdf, PDF page 16. ID: 2024S-A-Q041. Explanation written for this textbook.

Original question · Q41
Q41. The activities and milestones of a project are shown in the arrow diagram below. Which of the following is an appropriate description of the project if the duration of activity B is increased by 5 days? B F A 5 20 10 E H 10 15 C G 10 D 15 25 Legends Activity name Number of days required Dummy activity

Scroll horizontally to read the image at full size.