Original exam question · Select the image to enlargeRead the question as text
Q41. The activities and milestones of a project are shown in the arrow diagram below. Which of the following is an appropriate description of the project if the duration of activity B is increased by 5 days? B F A 5 20 10 E H 10 15 C G 10 D 15 25 Legends Activity name Number of days required Dummy activity