Monte Carlo simulation
1 related published questions. Take them one at a time.
- ITPEC Practice
- 0/1 answered
Question 1 of 1
0/1 answeredRead the question as text
A factory manager is planning the costs for the next two years. Instead of using a single estimate, the manager runs thousands of simulations where material prices, customer demand, and labor costs vary randomly within realistic ranges. This creates a probability distribution of possible costs, helping in risk planning and setting contingency budgets. Which of the following is an analytical method that the manager is using?