(1) Decision of procurement method
p. 224
Progress
Not marked complete
Related questions in this lesson 5
Request for proposal2Environmental criteria in green procurement2Weighted vendor proposal evaluation standards1p. 224 · PDF 228
(1) Decision of procurement method
This decides the procurement methods such as internal development and outsourced development. In cases such as outsourced development, if a vendor (i.e., subcontract company) is selected from multiple candidates, it is necessary to decide the bidding method.
- • Proposal competition bidding
Participants in the bidding are requested to submit a plan, and an order is given to the company with the highest score. - • Open bidding
Participants in the bidding are requested to submit an amount, and the order is given to the cheapest company.
(2) Decision of procurement details
This decides the details of the procurement such as what is in the scope of procurement, procurement requirements, and the procurement conditions. In some cases, an RFI (Request For Information) is issued to candidate vendors that describes the purpose of the
p. 225 · PDF 229
computerization, the details of business operations, and other information, in order to request the provision of information such as development experience of similar systems and the latest information technology. A candidate vendor that receives an RFI provides as much information as possible. The information is used for an investigation into the user‘s (or customer’s) procurement details.
(3) Decision of vendor selection standards
(4) Request for proposal
- • Proposal
This is a document that provides responses (e.g., system configuration, development method) with regard to the request. - • Quotation
This is a document that indicates the estimated amount (i.e., price) for the RFQ.
(5) Selection of vendor
The proposal or quotation is evaluated and selected by using vendor selection standards to examine the development certainty, reliability, cost break-down, schedule for each process, the final delivery date, and other aspects, and then the approval of the executives is obtained.
(6) Procurement risk analysis
p. 226 · PDF 230
(7) Conclusion of a contract
An official contract is concluded on the basis of agreement with the vendor. A contract (purchase order/order acknowledgment) is created according to the type of contract such as a (quasi-)mandate contract or service contract on the basis of the software development outsourcing basic contract model (proposed by JISA (Japan Information Technology Services Industry Association)) or the “information system/model transaction contract” (proposed by METI (Ministry of Economy, Trade and Industry)), and so on. At the same time, other agreements are concluded, such as an intellectual property right license agreement.
(8) Delivery
Deliverables that are delivered by the final delivery date are subjected to an acceptance test (i.e. receiving inspection) and other measures to provide confirmation that the requirements are fulfilled.
Section progress
Original chapter exercises
Original chapter exercises →New FE Textbook Vol.2 · First Edition, April 2015