Volume 2 · Chapter 5 · Textbook Exercises · Q9

Original textbook exercise · Select the image to enlarge
Read the question as text

The table below shows the relationship between preparation activities A through E for an event, the standard number of persons in charge for each activity, and the number of days required for each activity. On the basis of this table, preparation activities were started 35 days ago, but because of other activities only one staff member was assigned for the first 20 days. In order to perform the remaining preparation activities in time for the event, what is the minimum number of staff members that must be assigned per day? Here, each preparation activity has a manual, therefore, anyone can perform any activity and the activities can be performed in parallel. Editorial accessible table transcription: Preparation activity; Standard number of staff members; Required number of days. A: 2, 5. B: 2, 5. C: 3, 10. D: 2, 5. E: 5, 10.

The original image above preserves the complete textbook wording and layout.

Choose your answer
Choose an option to check your answer.
1 / 2

Source: FE Vol 2.pdf, PDF page 348, textbook p. 342 · Information-technology Promotion Agency, Japan · First Edition: April, 2015. ID: tb-v2-c5-q9. Publisher answer and commentary · private review.

Original question · Q9
The table below shows the relationship between preparation activities A through E for an event, 
the standard number of persons in charge for each activity, and the number of days required for 
each activity. On the basis of this table, preparation activities were started 35 days ago, but 
because of other activities only one staff member was assigned for the first 20 days. In order to 
perform the remaining preparation activities in time for the event, what is the minimum number 
of staff members that must be assigned per day? Here, each preparation activity has a manual, 
therefore, anyone can perform any activity and the activities can be performed in parallel.

Editorial accessible table transcription: Preparation activity; Standard number of staff members; Required number of days. A: 2, 5. B: 2, 5. C: 3, 10. D: 2, 5. E: 5, 10.
a) 4
b) 5
c) 6
d) 7

Scroll horizontally to read the image at full size.