Three-point duration estimation
1 related verified questions. Take them one at a time.
- Textbook Exercises
- 0/1 answered
Question 1 of 1
0/1 answeredRead the question as text
In a project, an activity that an experienced employee can complete in one day, can be completed in two days by a general employee. When a new employee who is not yet familiar with the work performs the same activity, it takes six days to be completed. Which of the following is a technique to estimate the period that is required for the activity as three days by the expression that is described below? Estimate of the duration that is required for the activity = (1 + 2 + 6) ÷ 3 = 3 days
The original image above preserves the complete textbook wording and layout.
Source: FE Vol 2.pdf, PDF page 346, textbook p. 340 · Information-technology Promotion Agency, Japan · First Edition: April, 2015. ID: tb-v2-c5-q4. Publisher answer and commentary · private review.