2026 Spring · Subject A · Q42

Original exam question · Select the image to enlarge
Read the question as text

The functional size of a new system was estimated to be 500 function points (FPs). Apart from development, the project requires 10 person-months in total for installation of the system and education of developers. Additionally project management requires 10% of the total person-months of development, installation, and education. How many person-months are required in total for this project? Here, the productivity in development is 10 FPs per person-month.

The original image above preserves the complete exam wording and layout.

Choose your answer
Choose an option to check your answer.
1 / 3

Source: 2026S_FE-A_Questions.pdf, PDF page 15–16. ID: 2026S-A-Q042. Explanation written for this textbook.

Original question · Q42
The functional size of a new system was estimated to be 500 function points (FPs). Apart from development, the project requires 10 person-months in total for installation of the system and education of developers. Additionally project management requires 10% of the total person-months of development, installation, and education. How many person-months are required in total for this project? Here, the productivity in development is 10 FPs per person-month.

Scroll horizontally to read the image at full size.