Function-point estimation
3 related verified questions. Take them one at a time.
- ITPEC Practice
- 0/2 answered
- Textbook Exercises
- 0/1 answered
Question 1 of 3
0/3 answeredRead the question as text
The functional size of a new system was estimated to be 500 function points (FPs). Apart from development, the project requires 10 person-months in total for installation of the system and education of developers. Additionally project management requires 10% of the total person-months of development, installation, and education. How many person-months are required in total for this project? Here, the productivity in development is 10 FPs per person-month.
The original image above preserves the complete exam wording and layout.
Source: 2026S_FE-A_Questions.pdf, PDF page 15–16. ID: 2026S-A-Q042. Explanation written for this textbook.