2024 Spring · Subject A · Q42

Original exam question · Select the image to enlarge
Read the question as text

Q42. What is the Cost Performance Index (CPI) of the project under the conditions listed below? Project Budget (BAC) 100,000 dollars Project Duration 4 months Elapsed Time 1 month Actual Cost (AC) 20,000 dollars Project Progress As planned

The original image above preserves the complete exam wording and layout.

Choose your answer
Choose an option to check your answer.
1 / 2

Source: 2024S_FE-A_Questions.pdf, PDF page 17. ID: 2024S-A-Q042. Explanation written for this textbook.

Original question · Q42
Q42. What is the Cost Performance Index (CPI) of the project under the conditions listed below? Project Budget (BAC) 100,000 dollars Project Duration 4 months Elapsed Time 1 month Actual Cost (AC) 20,000 dollars Project Progress As planned