1 related published questions. Take them one at a time.
- ITPEC Practice
- 0/1 answered
Question 1 of 1
0/1 answeredRead the question as text
Q54. A project was planned to be completed in six months. After six months, the project is behind schedule. The actual cost of Activity A is $100,000. The planned value of Activity A is $80,000. Activity A is only 75% complete. What is the schedule performance index and cost performance index of the project? Schedule performance index Cost performance index Source visual transcription: Planned six months;at six months Activity A is75% complete,actual cost$100,000,planned value$80,000. Original two-column choice values are transcribed in optionText.
The original image above preserves the complete exam wording and layout.
Source: 2023S_FE_AM_Questions.pdf, PDF page 19–20. ID: 2023S-AM-Q054. Explanation written for this textbook.