Volume 2 · Chapter 5 · Textbook Exercises · Q5

Original textbook exercise · Select the image to enlarge
Read the question as text

In a project, the performance management is conducted through EVM. Which of the following is the expression of the condition where the progress of the project is behind schedule?

The original image above preserves the complete textbook wording and layout.

Choose your answer
Choose an option to check your answer.
1 / 1Back to lesson →

Source: FE Vol 2.pdf, PDF page 346, textbook p. 340 · Information-technology Promotion Agency, Japan · First Edition: April, 2015. ID: tb-v2-c5-q5. Publisher answer and commentary · private review.

Original question · Q5
In a project, the performance management is conducted through EVM. Which of the following 
is the expression of the condition where the progress of the project is behind schedule?
a) EV − AC > 0
b) EV − AC < 0
c) EV − PV > 0
d) EV − PV < 0