When the activities of project quality management are classified into quality plan, quality assurance, and quality control, which of the following is an appropriate activity of quality assurance?

The original image above preserves the complete textbook wording and layout.

Choose your answer
Choose an option to check your answer.
1 / 1Back to lesson →

Source: FE Vol 2.pdf, PDF page 347, textbook p. 341 · Information-technology Promotion Agency, Japan · First Edition: April, 2015. ID: tb-v2-c5-q7. Publisher answer and commentary · private review.

Original question · Q7
When the activities of project quality management are classified into quality plan, quality 
assurance, and quality control, which of the following is an appropriate activity of quality 
assurance?
a) Deciding on the method for removing the cause of occurrence of unsatisfactory results 
for the quality standards that is defined in the project
b) Performing planned and systematic activities to ensure the fulfillment of the quality 
standards that is defined in the project
c) Inspecting whether or not the performance results of the project conform to the defined 
quality standards
d) Setting appropriate quality standards for the performance results of the project, and 
defining the procedures to satisfy the standards