Contents
Chapter 5 · Project ManagementPractice
← Return to textbook

CONCEPT PRACTICE

Push communication

1 related verified questions. Take them one at a time.

Filter questions
Question sources

1 of 1 questions match.

Textbook Exercises
0/1 answered

Question 1 of 1

0/1 answered

Volume 2 · Chapter 5 · Textbook Exercises · Q10

Original textbook exercise · Select the image to enlarge
Read the question as text

In a project, the project manager sends a report that contains the project performance to specific stakeholders through e-mail. Which of the following is the communication method that is implemented by the project manager?

The original image above preserves the complete textbook wording and layout.

Choose your answer
Choose an option to check your answer.
1 / 1Back to lesson →

Source: FE Vol 2.pdf, PDF page 348, textbook p. 342 · Information-technology Promotion Agency, Japan · First Edition: April, 2015. ID: tb-v2-c5-q10. Publisher answer and commentary · private review.

Original question · Q10
In a project, the project manager sends a report that contains the project performance to specific 
stakeholders through e-mail. Which of the following is the communication method that is 
implemented by the project manager?
a) Interactive communication
b) Feedback communication
c) Push communication
d) Pull communication